Norman housing estate. Construction company "Norman": reviews
founded in 2004 and serves as a customer, investor, developer and general contractor for residential real estate in St. Petersburg and the region. More than ten years of experience, the company already allows us to talk about it as a builder with experience.
In addition to construction organizations, Normann Group of Companies includes management Company "UK" Norma Dom ", a company for the repair and decoration of premises" Remstroyservis ", law firm" Normann-Consult ", information and analytical center" Norminfo. Since 2013, is a permanent mortgage partner.
Developer Normann builds houses of economy class and comfort class, focusing on the needs of the mass market. It happens that the houses from the Normann construction company are commissioned with slight delays. The average duration of delays is 5 months, the maximum is 15 months, report.
December 2015: based on the results of the outgoing year from the volumes of 2014, i.e. the volume of apartments sold has not changed.
February 2016: Normann construction company took the 9th place in terms of the volume of housing under construction in St. Petersburg and Leningrad Oblast. Currently, the developer is working on 300 thousand square meters. meters, a third of which will be commissioned this year. At the same time, several new facilities are starting: two successive stages of the Yarkiy residential complex and 2 new residential complexes; negotiations are underway to buy new land plots.
April 2018: Norman posted a notice of intent to file on se.fedresurs.ru bankruptcy petition their three companies. The developer says that this is primarily a technical measure to stabilize the situation with bankruptcy claims against it by former equity holders.
October 2018: during the 2nd and 3rd quarters of this year, the developer postponed the deadlines for all of his facilities except Normandy Residential Complex (but delays and rescheduling are also possible). For some of them for a year and a half. The question of the true bankruptcy of Norman is found in messages on our forum.
December 2018: In 2018, the company continues the construction of 9 residential complexes, for several of them the deadlines were postponed. The maximum transfer period is 39 months for ZhK Desyatkino. As the developer promises, apartment buyers must receive the keys to the first phases of the residential complex Moroshkino and the residential complex Bright before the end of the 4th quarter of 2018. There are 6 completed complexes in the company's portfolio.
January 2019: according to Fontanka, Vladimir Smirnov, general director and co-owner of the Normann Group of Companies, was detained on the eve of an especially large-scale fraud case. Editors say that Vladimir Smirnov was detained as a suspect for two days on January 30. The detention is connected with a criminal case, which the Main Investigation Department of the Main Directorate of the Ministry of Internal Affairs instituted under Art. 159 of the Criminal Code - fraud on an especially large scale. It goes about several objects that Norman is building.
June 2019: structures that are part of the Normann Group of Companies are going through a bankruptcy stage. The courts filed many lawsuits from defrauded equity holders. In May tax service filed a bankrupt lawsuit against Norman Service. In April, Vladimir Smirnov, the company's general director, was charged with especially large-scale fraud. According to investigators, the businessman raised 3.15 billion rubles from equity holders for the construction of the Desyatkino 2.0 residential complex in Murino. Of these funds, only 1.3 billion was spent on work. None of the facilities has yet been completed. In total, the company has 8 undelivered LCDs. She does not conduct construction at the facilities. And, more likely, according to the forecasts of real estate market analysts, it will officially cease to exist. The authorities of St. Petersburg and Leningrad region took the situation with long-term construction under their control. For four complexes -, and new contractors were found. In May, interest holders were announced new deadlines for completing the construction of complexes.
Now, according to the website of the arbitration court, at five stages of bankruptcy there are five companies belonging to the Normann group: Normann-Stroy, Normann-LO, Normann Zapad, Normann Yug and simply Normann. The developer at various stages of construction has seven residential complexes of 13 houses with total area more than 320 thousand m2 in St. Petersburg and the Leningrad region.
Apartments are waiting for 6.2 thousand interest holders. The amount of obligations "Norman" to them exceeds 4 billion rubles. The delay in completion of construction is from 1 to 2.5 years. According to Vladimir Smirnov, co-owner of Norman, now the company has all accounts seized bailiffs, also in Rosreestr blocked the possibility of registering new DDU.
“We are now considering different possibilities for completing the construction. It will either be the sale of land, for example, for Normandy residential complex, and other assets. Maybe it’s attracting project financing from one of the state banks or attracting investors to complete one or all of the objects and transfer them all obligations to equity holders, "said Vladimir Smirnov. “The work is going on in all directions, but it’s very difficult. Either our conditions do not suit investors, or investor proposals do not suit us. My goal is to do everything possible to finish building houses. Our deadline is December 2018. Until that time I’ll try to solve the problem, "the owner of Norman promised. Otherwise, all his companies will be bankrupt and their fate will be decided by the court.
However, according to Dmitry Nekrestyanov, head of real estate and investment practice at Kachkin & Partners, bankruptcy is one way to solve the company's problems. "Which is better - there is no definite answer. Bankruptcy does not mean that they will not build: it all depends on so many factors and goals of all participants in the process. Moreover, if earlier the construction sites were really frozen for a long time, then according to the new law the terms are much shorter. Yes and completion options in bankruptcy have now changed, ”he says.
“The situation with the company is 50/50: it will either complete or not complete. We help the developer with what we can, but our capabilities are limited, we cannot solve business problems for him. In fact, we can only help in negotiations and guarantee the performance of state functions the implementation of the project and some control over the observance of the rights of interest holders. For example, in the event of bankruptcy, we will enter the process by third parties to protect their rights, "said Mikhail Moskvin, Deputy Prime Minister of the Leningrad Region. According to him, it is extremely difficult to attract investors to complete the projects: for example, in the spring negotiations were underway with Liga Estate to transfer the Bright World project to Yanino, but the new developer could not find the money to continue the construction.
Three residential complexes of the company are under construction in St. Petersburg: Izhora Park, On Zarechnaya and Three Oranges. “For each of them, the degree of readiness was determined, and given the difficult financial condition of the company, a decision was made to streamline the construction in order to ensure effective financing and speedy completion of the construction. The Committee, together with the relevant executive authorities, regularly holds field meetings at all facilities, including the participation of initiative groups of interest holders to control the dynamics and regulate the construction and installation works, "they say in the city construction committee.
"All of the builder’s main forces and resources are directed to the construction of Izhora Park, after which labor, contractors and financing will be transferred to complete the construction of the Na Zarechnaya complex. And then to the Three Oranges residential complex. At the same time, the builder doesn’t stop work at any facility, ”the DP assured the press service of the department.
As Vladimir Smirnov assures, four objects will be commissioned. Already in the III quarter of 2018, the company plans to commission the last houses of the Izhora Park residential complex. Also, the developer promises to hand over the projects "On Zarechnaya", "Three Oranges" and the first stages of the regional object "Desyatkino".
The Normann group in 2004 was founded by Vladimir Smirnov, Yuri Rafalsky and Igor Vitkovsky. In the 2000s, they actively developed the production of building materials and contracting. The holding North-West Non-Metallic Company included about 20 enterprises for the extraction of sand, gravel, Taxi-Concrete and ISG Normann. At the end of the 2000s, Yuri Rafalsky became involved in politics: he joined the United Russia, and in 2010–2011 he held the post of deputy head of the Republic of Karelia. Igor Vitkovsky focused on his own Intratul company, while Normann came under the control of Vladimir Smirnov.
Select the fragment with the error text and press Ctrl + Enter
The authorities of St. Petersburg and Leningrad region are actively struggling with problematic objects. Soon there will be no long-term construction projects and deceived equity holders, pickets and rallies will be a thing of the past. The real estate market will become boring and predictable. Who was lucky last year?
Last year, through the joint efforts of the authorities and developers, the city managed to get rid of 20 problematic construction projects. According to the website of the Government of St. Petersburg, over 280 thousand "squares" of housing were commissioned. The keys to the long-awaited apartments will be acquired by 6,320 equity holders.
In November, builders became more bankrupt, and fewer billionaires. Deceived investors are again unhappy. One of the "Norman" unfinished buildings was commissioned, but the story may turn out to be a criminal continuation.
November 25 “The Normann Investment and Construction Group has extended the permit for the construction of the residential complex“ On Zarechnaya ”(the object is being built on section 5 along the Olga road). Permits were extended by the State Construction Supervision Service of St. Petersburg to the houses of the first, second and third stages of construction. For the first stage, the deadline was extended until March 31, 2020, for the rest - until December 31, 2022.
Holders of LCD "Izhora Park" whole last month they were waiting for this event. Note that the conclusion of compliance was received by the developer on October 23. Usually, between a receipt of an AIA and submission of documents for commissioning, a couple of days.
Last weekend, interest holders LCD Three Oranges went on a picket to their unfinished house. This picket was the first after the builder was declared bankrupt. The townspeople expect that the protest rally will attract the attention of not only the authorities, but also a potential investor who is able to complete the problematic facility. This time the children went to the picket.
Military action is taking place immediately in 75 regions of Russia. The participants in the confrontation are deceived equity holders and officials. According to the United information system housing, in the Russian Federation, there are just over 3 thousand problem houses. But in early October, the press service of the Accounts Chamber of Russia denied official data, it turns out that in Russia there are more than 70 thousand long-term construction projects. Among them there are houses that cannot be completed for more than 20 years. In Russia, a generation of deceived equity holders has grown.
On the eve - on the night of all saints - the head of the Normann construction company wrote a complaint to the court. He asked the court to consider the appeal, release him from custody, and for this he promised to transfer to the real estate investors of the third stage of the residential complex “On Zarechnaya” the documents for the object.
In October, new metro stations appeared in St. Petersburg, part of the defrauded equity holders became new residents, the less happy part awaits the visit of the governor, but he does not go.
Today, interest holders LCD "Desyatkino 2.0" went on a picket to the building of the government of the Leningrad region. The deceived shareholder and mother of many children explains that her protest is a necessary measure, so she hopes to draw the attention of the authorities to her long-term construction.
The deceived real estate investors of the Desyatkino 2.0 LCD are sure that they will be able to get their apartments only after changing the law. On the eve of the request for reforms 214-FZ, they handed over to the Deputy Prime Minister of the Russian Federation - Vitaly Mutko.
Rested after the summer holidays, developers, interest holders, lawmakers with fresh energy rushed to fight, build, rally. And it seems that everyone has one goal, but the approaches to implementation are different.
Interest holders, having defeated the developer, are preparing for the next battle in court. This time, Vladimir Smirnov, the head of Normann Group of Companies, asked to let him out from under the experience so that he could complete all the unfinished buildings while at home.
Today, Smolny admitted that by December 31, 2019, only one unfinished construction abandoned by Normann will be introduced. Recall, it was previously stated that by the New Year holidays all three will be introduced - LCD “On Zarechnaya”, “Three Oranges”, “Izhora Park”.
August was fun in the market. Everyone who could celebrated the day of the builder and boasted of their success. Between the festivities, officials traditionally fought against long-term construction projects, deceived equity holders traditionally fought with developers who had nothing to celebrate on Builder's Day.
The general collection of signatures under the appeal to the court has been announced by the holders of the residential complex “Desyatkino 2 .. Those who invest in the unfinished building are afraid that the director general of Normann, Vladimir Smirnov, may avoid punishment.
Today, August 19, the Arbitration Court is to reach a verdict declaring Normann to be bankrupt. A lawsuit against a construction company was filed by one of the customers, but one of the companies, which according to the Unified State Register of Legal Entities, was established by the owner of Normann Group of Companies Vladimir Smirnov, bought her lawsuit. Interest holders do not exclude that the Norman customer will withdraw the bankruptcy lawsuit altogether.
The Government of the Leningrad Region received the first certificate in Russia on registration of the Non-Profit Organization "Fund for the Protection of the Rights of Citizens-Participants in Shared Construction". Personnel and organizational procedures will be completed in the next two weeks.
The author of the poem is Nadezhda Filatova. One of those who gave Normann money to build an apartment in three eighteen-story high-rises of the Desyatkino 2.0 residential complex. Recall that LCD sold more than 95% of the apartments. After several transfers, the developer made the last promise to equity holders: to hand over the second stage of the Desyatkino 2.0 residential complex - building 3 - already at the end of 2019, and first of all - buildings 1 and 2 - in the first half of 2020.
Message that regional fund activists waiting for the completion of the residential complex “Desyatkino 2.0” received registration of the interest holders in the Ministry of Justice late in the evening. A week ago they were promised that a fund that would give money for building a house would be created immediately after registration of the documents.
“The estimated timeline for completion of the first stage of the residential complex“ On Zarechnaya ”and the residential complex“ Three Oranges ”is 12/31/2019, and the third stage of the“ On Zarechnaya ”- 05/31/2021, - shared interest from Smolny on behalf of Alexander Beglov, - At present, specialized public authorities of St. Petersburg are conducting joint negotiations with prosecution authorities, the developer and investor of the facility regarding the early completion of all Normann construction projects, including the housing complex on Zarechnaya and Three Oranges. "
There is not much good news. Only, perhaps, in Kudrovo. More than a million problem square meters were found in the Leningrad region. The authorities are not able to cope with these unfinished projects. Interest holders are starving. Developers are planting.
Low-rise construction is going through hard times. The scandals associated with comfortable housing projects in the country at the price of a studio in St. Petersburg have spoiled the image of this real estate format. It is not only the developers who are guilty of this who led an unreasonable, and sometimes criminally punishable, monetary policy.
“They require a deep analysis of the reasons for the double increase in the first half of the number of problematic shared construction objects from 894 to 1,845. As well as the increase in the number of defrauded equity holders by six thousand people — from 38.7 thousand to 44 thousand people,” said Prosecutor General Yuri Seagull, summing up the work for the first half.
This morning, interest holders, deceived by the Normann construction company, announced the end of the hunger strike. The result of the five-day campaign is as follows: one of the women, who was taken out of the construction site by ambulance, is still in the hospital, three other hungry people went home.
That night at the construction site in the village of Pargolovo (Olginskaya road, section 9) it was crowded. True, there were no builders, but there was a police outfit and four equity holders of Normann Group of Companies. And one of the last was starving. The rest guarded her.
The action began on July 25 at exactly 4 p.m. The hunger strike, according to activists, is stepping up work to complete the residential complex “Three Oranges” and “On Zarechnaya”. As the townspeople explain, they were forced to take this step by the refusal of the Normann Group management to sign an agreement with the investor, which was found by the St. Petersburg state construction supervision.
Lobing is a thing of the past. With each month of the projects that are implemented according to the usual scheme, there will be less. Almost all new properties that go on sale after July 1 will use banking project financing. (Except for a few who are ready to build "on their own" and sell the finished).
“The construction of the second stage of the Desyatkino residential complex will be completed within the framework of the bankruptcy law: shareholders will unite in ZhSK, and the government will look for a new investor,” the site was told in the press service of the regional administration.
Statement of claim one of 600 holders of the Izhora Park LCD filed an arbitration court. The amount of claims is 3.8 million rubles. The plaintiff demanded to declare LLC Normann-Yug bankrupt and return the money in full.
Our family has enough living space. But suddenly my mother (she helped raise my daughter for many years) stated that she wanted to take a break from us. I really understand her and therefore agreed to purchase an apartment. To save money, I decided to give money for an apartment that is still being built.
Today, workers in the Izhora Park residential complex painted and plastered the walls in the third and fourth sections. In addition, we completed the installation of electric floorboards on the floors. And they carried out work on the sealing of stained glass structures on balconies. Also mounted brick walls in commercial and technical premises.
First of all, they will start building two houses from the bankrupt Normann Group of Companies. Part of the funds for these purposes will be allocated by the regional budget, and part by the federal. In “Yarkiy” residential complex and “Desyatkino 2.0” residential complex, in order to prepare an estimate for DOM.RF, the counting of creditors and concluded equity contracts began.
Deceived equity holders during the days of the economic forum picketed the representative office of the President of the Russian Federation in St. Petersburg, the government building of the Leningrad region, the consulates of Germany and France, and the entire Nevsky Prospect. According to the calculations of the activists, 70 defrauded real estate investors of the Leningrad Region went to solitary pickets, which were held at the Expoforum and the Anichkov Palace, as well: each of them had a poster with the requirements.
Despite the May holidays, which “took a bite” of the whole working week, spring over-activity reigned in the market of new buildings, compensating for the many-day rest. And here we have it. Investigators decided to come for a developer-deputy, the governor of the Leningrad region strictly asked the impersonated developers to get out of the region. And in St. Petersburg, they dream of a new ring and are preparing for the election of governor.
The day before, an open letter appeared to the governor of the Leningrad region. The author of the appeal, the deceived real estate agent Pavel Zhdanov, explains that he now has only such a way to communicate with the head of the Leningrad region.
April was seething with events. The activity of Petersburgers grew before our eyes. The deceived investors did not bother much and faded into the background. And on the first - topics are not about housing, but very related to it.
Until recently, only Normann-West (the developer of the Moroshkino residential complex) was declared insolvent. On the eve of court of Arbitration declared bankrupt “Norman LO” (the developer of two phases of RC “Desyatkino” in Murino and RC “Bright” in Yanino).
Today it became known that the State Construction Supervision of St. Petersburg extended for four years the validity of the building permit “Normann-Center”: the company is building in Pargolovo apartment house with built-in rooms, ground garage (car park), underground garage (car park) and transformer substation.
Yesterday, a regular meeting was held at which the resumption and completion of the construction of several residential complexes in the Leningrad Region was discussed. Previously, Normann has attempted to build houses, but now the completion of the construction is a big question.
According to cEO company of Vladimir Smirnov Normann will receive loan financing for the completion of the second phase of the residential complex "Desyatkino" in Murino. Work on the construction site is scheduled to resume in February this year.
This year, developers have rented more housing than the authorities planned. Some companies successfully implemented their first project and became full members of the elite club of St. Petersburg developers. Some were out of luck. To summarize briefly.
The authorities intend to prohibit all developers who have projects with defrauded real estate investors from registering new transactions for the sale of assets. Officials believe this will help discourage the illegal withdrawal of funds from the company.
According to the participants in shared construction, the water level in the basements of all three buildings reached the ceiling. In this regard, they are going to hire a liquid pumping company, and independently eliminate the violations identified by the State Construction Supervision Agency.
It was planned that the last 2 buildings of the complex will be commissioned in 2015. Then the dates were repeatedly shifted. The final date for the completion of the construction was the end of 2018, but this time, as the Committee for the Construction of St. Petersburg found out, there is no need to transfer.
Housewarming in the company of unpacked building materials and unfortunate companions has become a tradition for Russian equity holders. Last year, Muscovites made noodles on bags of cement in the LCD "Val d" Emerol, this year - St. Petersburg residents in the LCD "Izhora Park."
Gosstroynadzor once again extended the developer Normann permission to build a residential complex "Zarechnaya". Interest holders are not hoping to get the keys to the apartments before the end of this year. The first phase should have been completed in 2016.
Normann Construction Company was established in 2004 to implement housing development projects. Investment and construction group "Norman" is a promising and dynamically developing enterprise operating in the field of housing construction. Normann operates in the construction market of St. Petersburg, acting simultaneously as a general contractor, customer and investor.
Normann ("Norman") is building residential complexes with reasonable savings, which allows to reduce the cost of apartments and make them more affordable.
To date, the company "Norman" has erected four objects:
- The Kolomyagi Breeze Club House is a five-story building for 29 apartments located in Kolomyagi, a historic district in the north of the city;
- The residential complex "Two Captains", which consists of two high-rise (20 and 22 floors) brick-monolithic houses. The complex is located at the intersection of Kuznetsov Avenue and Leninsky Prospect.
- 16-storey building, built on brick-monolithic technology and located in the Moscow region, one of the most prestigious districts of St. Petersburg
- Nevskaya Vertical is a 17-storey building located on Vitebsk Prospect, in the prestigious district of the city - Moskovsky.
Six more objects of the Norman construction company are in the stage of active design and construction:
- Brick-monolithic houses on 5 floors located in Vsevolzhsk;
- Brick-monolithic high-rise residential building "Excellent" (22 floors), located on the Ave Industrial;
- Located in the village of Shushary, a brick-monolithic 19-storey residential complex;
- The low-rise cottage village “Normandy”, which consists of 267 townhouses and is located in Kolomyagi, the historical district of St. Petersburg;
- The residential complex “Izhora Park” planned for construction. According to the project, it will be a composition of five brick-monolithic houses, in each of which 12-18 levels are planned. The complex will be erected in the PGT Metallostroy;
- The residential complex "On Zarechnaya" in Pargolovo is at the design stage
Each of the projects created by Normann meets the requirements of high-quality and conscientious development, providing the most comfortable living conditions.
The Norman construction company has existed in the economy class housing market since 2004. In her work, she is guided by the postulate that each family should have a separate apartment.
CJSC "Norman"
Since its foundation, Normann Investment and Construction Group CJSC has been part of the SNZK holding. Having built up capacity and gaining experience, in 2006 she began to independently engage in the development of real estate (development). The company is building affordable homes for middle-income residents.
Normann is both a customer, investor, developer and general contractor. This means that the company carries out the entire construction process, starting with the design and execution of permits and ending with the commissioning of facilities. In her activities, she uses new technologies and developments. The region in which Norman operates is St. Petersburg and the Leningrad Region.
House for rent
- The Neva Vertical.
- "Vitebsk".
- "Shushary."
- Kolomyagi Breeze, 5-storey building.
- “Two Captains”, 22-storey.
- "In Vsevolzhsk."
- "Excellent" in 22 floors.
- Izhora-Park (the second phase was commissioned, but the apartments have not yet been settled).
Residential complexes under construction
- "Desyatkino", "Desyatkino 2.0" (Vsevolzhsky district).
- “On Zarechnaya” ( Vyborgsky district SPb). 1st stage commissioning - 1st quarter 2016, 2nd-4th quarter 2017 year
- "Three oranges." 1st turn - 4th quarter 2015, 2nd - 1st quarter 2016 year
- "Bright". 1st turn - 1st quarter 2017 year
Prospects
Currently designed LCD "Normandy" (Kolomyagi) and "Moroshkino". Norman plans to become a leader in the construction of economy class apartments in its region. To this end, she intends to work in other areas and provide customers with additional services.
LCD "Desyatkino 2.0"
Back in July 2014, he received permission to build the first phase of this Normann housing complex. The construction company Desyatkino 2.0 is building Murino in the suburbs of St. Petersburg. Two weeks later, she began to sell apartments, future residents. Permission to build the second phase was received in September of the same year.
Norman is not the only developer on this site. RC "Three whales" erects "SU-155", as large as the "Normann" construction company. Desyatkino 2.0 is a short walk from the Devyatkino metro station. The infrastructure of the microdistrict is expanding. Planned equipment playgrounds for children and adults.
According to the schedule, the first stage should be completed in the second quarter of 2016, the second - in the fourth quarter of 2017. But it is not known whether the Desyatkino complex will be ready for the deadline. "Norman" in the spring delayed the progress of construction for three months.
LCD "Izhora Park"
Not only in the open field is building a Norman house (construction company). Izhora Park is being built in the historic center of Kolpino. It will consist of five brick monolithic buildings, 12- and 18-story. The first stage (two buildings) was commissioned, the term of the second stage is the 4th quarter. 2015 year. Price one-room apartment - 1.85-2.86 million rubles.
The ceiling height in these houses is 2.7 m. It will make it possible to install furniture and live comfortably. The interior doors in the apartments will be wooden, the entrance - metal.
In the decoration of the facade plan to use ceramic brick. Heating will be carried out using an autonomous gas boiler.
Planned traditional parking. The territory of the complex will be guarded. Each house will have a concierge, in apartments - intercoms with the possibility of subsequently installing video surveillance.
The Rybatskoye metro station is located five kilometers from the construction site. - 70 meters from the construction site.
Major infrastructure facilities are nearby. There are no entertainment facilities yet. Although, after the commissioning of the complex, they can be located on the ground floors, as indicated in the development plan provided by the Norman construction company.
Responses of residents of the neighboring microdistrict claim that under the complex passes. These places have long been called swamps. Because of this, it’s supposedly impossible to build here. But the examination did not confirm these opinions. Buyers hope that the developer has strengthened the soil under construction.
The second section was put into operation three weeks later than the plan (in January), but settlement will occur before July 2015, as the Norman construction company says.
Customer reviews indicate that many people buy several apartments, especially for resale or for rent. They believe that this is a profitable investment.
At first, when they were still digging a pit, the Norman construction company offered relatively low apartment prices. Customer reviews indicate that it is at this moment that it is profitable to buy an apartment there, having paid all 100%. Then prices begin to rise monthly like a snowball. And at the time of delivery they reach the value of the apartments of the remaining developers.
A mortgage can be issued at a bank owned by the Norman construction company. The bank takes so high interest that it is more profitable to take consumer credit. Reviews say that buying an apartment by installments is unprofitable.
With a delay of six months. Employees explain it as inconsistency with the authorities of the project for the planning of territories.
LCD "On Zarechnaya"
In the second quarter of 2015, the first phase of the Na Zarechnaya complex should be commissioned. It is also erected by Norman (a construction company). Prices are reasonable: square meter It costs from 63 thousand rubles.
The complex in Pargolovo will consist of five residential buildings, the construction of which is carried out in three stages. In December 2014, “Normann” began to build the second phase of the residential complex “On Zarechnaya”. It will have two buildings and will consist of houses on the 19-25 floors, equipped with modern high-speed elevators, metal-plastic windows, glazed balconies. In the houses of the third stage they plan to hold loggias. On the territory of the complex will operate food and hardware stores, a fitness center, pharmacy, office premises. They plan to garden the yards.
The territory of the housing complex will be protected by a fence. The presence of intercoms will help to avoid access by strangers. For parking, parking and outdoor areas will be built. Parnas Metro Station is 9 km away.
Apartments are planning to rent without finishing. The price of a studio with an area of \u200b\u200b22 m 2 is 1 million 35 thousand rubles. The average delay in the completion of Normann facilities is 3 months, and the maximum is 15 months.
In January 2015, the construction process of the Zharkiy residential complex was launched, which should be completed in 2017.
February 2014: received houses, mainly consisting of studios, in the residential complex "Moroshkino" (Vsevolzhsky district). The deadline is the end of September 2016.